For more than 30 years, officials have talked about making the intersection of Federal City and Bull Run roads safer. Now, after decades of studies, proposals and disagreements, a solution may finally be in sight.
Ewing, Hopewell and Lawrence townships are moving forward with a $2.19 million project that would replace the long-discussed traffic signal with a roundabout and bring additional improvements to nearby Federal Point Boulevard.
The Hopewell Township Committee approved an agreement Monday, Nov. 9, establishing how the three townships will share the costs and responsibilities for the project. The agreement moves forward a long-planned effort to address traffic safety concerns where the boundaries of the three municipalities meet.
Ewing, Hopewell and Lawrence townships will jointly host a public information session Wednesday, Dec. 9, at 6:30 p.m. at the Hopewell Forge Clubhouse, 100 Forge Circle, Pennington. Residents from all three communities are invited to review the proposed improvements, meet with project engineers and ask questions.
Ewing Township is coordinating the project and secured funding through the New Jersey Department of Transportation’s Local Transportation Projects Fund. A preliminary budget places the total cost at approximately $2.19 million, including about $936,000 for the roundabout and nearly $698,000 for traffic signal improvements.
The remaining expenses include engineering, construction oversight, property acquisition and other work associated with completing the improvements.
The agreement identifies $1.35 million in state funding, leaving approximately $841,000 to be divided equally among the three municipalities. Each township’s estimated share is $280,343.
The latest funding figure is greater than the $800,000 state grant Ewing announced in January. The available information does not explain the difference between the two amounts.
The agreement also establishes responsibilities for maintaining the roundabout and traffic signal after construction is completed. The project remains in the planning and design stages, and a construction schedule has not been announced.
The project addresses two nearby intersections that have generated traffic concerns for different reasons. At Bull Run Road, officials have focused on traffic speeds and safety, while at Federal Point Boulevard, concerns have centered on vehicles entering Federal City Road from residential developments and nearby businesses.
The Federal Point Boulevard intersection serves Traditions at Federal Point, an age-restricted residential community in Lawrence Township, and the 300-unit Woodmont Forge at Hopewell apartment development on the opposite side of Federal City Road. Several office buildings and a day care center along Federal Point Boulevard also contribute to traffic entering and leaving the intersection.
Residents of Traditions previously raised concerns about additional traffic associated with Woodmont Forge and the difficulty of entering Federal City Road. Those concerns helped prompt renewed discussions among officials from the three townships about improving both intersections.
In 2024, a traffic study prepared by Arora and Associates concluded that traffic signals were warranted at Bull Run Road and Federal Point Boulevard. The study also recommended separate left-turn lanes in both directions on Federal City Road at Federal Point Boulevard.
Lawrence Township Council awarded a $46,270 contract to Remington Vernick Engineers in June 2024 to prepare the design and construction specifications for a signal at Federal Point Boulevard. At the time, the municipalities had not reached an agreement on how to divide the costs of the proposed improvements.
Lawrence officials wanted to proceed with the Federal Point Boulevard signal, while Ewing and Hopewell officials emphasized an earlier understanding concerning a traffic signal at Bull Run Road.
Hopewell officials questioned whether a signal was needed at Federal Point Boulevard, citing an earlier traffic study associated with Woodmont Forge that reached a different conclusion. Then-Hopewell Township Mayor Courtney Peters-Manning also raised concerns that installing a signal could cause traffic to back up toward Interstate 295.
Lawrence’s subsequent study supported installing the signal, and the township moved forward with preliminary engineering. Meanwhile, discussions about the Bull Run Road intersection began moving in a different direction.
By May 2025, Ewing was pursuing state transportation funding for a roundabout rather than the conventional traffic signal that had been discussed for decades.
At a May 20, 2025, Lawrence Township Council meeting, Municipal Manager Kevin Nerwinski explained that Ewing was working with Mercer County officials on the roundabout proposal because they believed it would be more effective at calming traffic.
Lawrence Council approved a resolution supporting Ewing’s application for state funding, which included the roundabout and improvements at Federal Point Boulevard. At the time, Nerwinski told council members that supporting Ewing’s proposal would not create an additional financial obligation for Lawrence or interfere with its existing plans for the Federal Point Boulevard signal.
The latest agreement establishes a financial commitment from all three municipalities toward the combined project.

Unlike traditional intersections controlled by traffic signals, roundabouts require entering vehicles to yield to traffic circulating around a central island. The design generally reduces vehicle speeds and eliminates many of the crossing movements that can result in serious crashes at conventional intersections.
Roundabouts also allow traffic to continue moving when there is a safe opening rather than requiring vehicles to stop for a signal cycle.
The idea of improving the Bull Run Road intersection dates back more than three decades, according to Hopewell Township Planning Board records.
A development approval granted July 21, 1993, to K. Hovnanian Companies of Central Jersey included provisions for participation in Mercer County’s Transportation Development District program, which contemplated improvements that included a signal at Federal City and Bull Run roads.
A November 1999 memorandum from the Mercer County Division of Planning subsequently discussed a $400,000 contribution from Hovnanian toward the traffic signal. Despite those earlier plans, the signal was never installed.
The historical records do not establish whether the contribution was collected or what ultimately happened to the money.
The earlier proposal resurfaced in 2019 and 2020 during a dispute over Hopewell Township Planning Board approval of Woodmont Forge. Residents concerned about traffic safety challenged aspects of the development approval, arguing that longstanding problems at Federal City and Bull Run roads had not been adequately addressed.
Their attorney, Edward M. Bernstein, submitted the 1993 approval and 1999 county memorandum as evidence that improvements at the intersection had been considered for years. The residents sought to reopen or reconsider the Planning Board’s approval of the apartment development.
Woodmont’s representatives opposed the request, maintaining that the Hovnanian approval concerned a different development and did not establish an obligation for Woodmont to finance the traffic signal. The developer’s traffic consultant estimated that Woodmont would increase peak-hour traffic at the Bull Run Road intersection by no more than 3%.
At its June 25, 2020, meeting, the Planning Board rejected the residents’ request to reconsider the development approval. The board accepted the developer’s traffic analysis and determined that the projected increase was insufficient to require a contribution toward an off-site traffic signal.
The board also concluded that efforts to improve the intersection should be pursued through Mercer County and the governing bodies of Ewing, Hopewell and Lawrence rather than through the Woodmont development application.
That determination placed responsibility for addressing the intersection with essentially the same governments now working together on the roundabout.
When Ewing announced the initial state funding in January 2026, Mayor Bert H. Steinmann described the proposed improvements as an investment in public safety and regional transportation.
“This is a significant investment in public safety and regional mobility,” Steinmann said.
“This intersection has long presented challenges, and the roundabout will provide a safer, more efficient solution,” he said. “We’re grateful to NJDOT for recognizing the importance of this project and to our neighboring municipalities for their continued partnership.”
Lawrence Township Mayor Christopher Bobbitt also welcomed the state grant and the cooperation among the municipalities.
“I see this support from NJDOT as a win for all three municipalities and the nearby residents,” Bobbitt said. “By working together, the roundabout at Bull Run Road and the related traffic improvements will make this section of Federal City Road safer for everyone.”
Hopewell Township Mayor David Chait similarly emphasized the regional nature of the improvements.
“This project demonstrates the value of strong regional collaboration and a shared commitment to safety,” Chait said. “The improvements will benefit residents and commuters traveling through our communities every day.”
Hopewell Township also introduced a bond ordinance Nov. 9 that would redirect $150,000 in previously authorized borrowing toward the Federal City Road improvements.
The money originally had been designated for a traffic signal at Federal City and Bull Run roads. The ordinance would allow the funding to be used for the revised project, including the roundabout.
The measure requires a public hearing and final approval before it can take effect.
Work remaining before construction includes completing the engineering plans, addressing property and right-of-way requirements, and preparing construction documents. The preliminary budget includes funding for those activities, although actual costs could change as the design is finalized and construction bids are received.
At the Dec. 9 public session, engineers are expected to present the proposed roadway configuration, answer questions and discuss how the changes are intended to improve traffic safety and circulation. Residents and nearby property owners also will have an opportunity to raise questions about access, traffic patterns and other potential effects of the project.
The municipalities have established how they intend to divide the financial and maintenance responsibilities, but the final design, construction schedule and actual cost of the improvements have yet to be determined.